Lets start at the ending!  Here is the Crusader with her new bottom.   As you can see she floats considerably above the water line she had when she was delivered. (We repainted it in the same position!)

From Hancock Point she headed home to the Boston area.

This is the apron of the keel once she was opened up and the new wood in place.  A rabbet was cut into the curve to accomodate the existing ribs.  Sheer muscle was used to spring the ribs apart enough to get the piece in there!

This photo shows the keel apron before we muscled it into place. It also shows the new chine piece. At the very right hand edge of the photo you can see the support used for the front of the boat once the apron was being opened up. This was to ensure that the boat would not lose her shape.

Here is the apron with garboard plank in place.  At this point the support has been removed and the boat is again secure on her keel.

When doing a restoration project it is important to keep the wood covered with something after stripping.  This transom was stripped mostly by sanding, and then a base coat of varnish cut with 75% thinner, was applied with in 24 hours.  We did not want the sun to bleach the beautiful color of the natural mahogany.

This shot shows the replacement frames in the transom and a part of the new starboard chine.

You can also see the transom is all varnished now.  It has 8 coats of Captain’s Spar Varnish, sanded and tacked between most of the layers.  I have found that if I catch the varnish at just the right point I do not need to sand or tack between layers.  This is tricky and the humidity level has to be just perfect to pull it off!

Here is Marshall in front of the bow, much of the rotten material has been removed but as you can see there was still some to go before hitting solid material.

Here is the bow with the new stem and new planking in place.  Mahogany was used for both the stem and the planking, fastened with silicon bronze (as were used through out the project) and bedded in 3M 5200.

HomeRestoring an Old Town RunaboutRecanvas a CanoeCC New BottomTraditional PramsNew Construction
Guest BookMeet UsOur PolicyQuestions and AnswersBoats for SaleNew Toe Rail

Contact: Marshall and Jo Duhaime, Jr.
3 Duhaime Drive
Hancock, Me.04640

email:  prambuilder at yahoo dot com